enConstruction starts: Strathcona Anatomy and Dentistry – Laboratory renovations for new electron microscopes
/facilities/channels/news/construction-starts-strathcona-anatomy-and-dentistry-laboratory-renovations-new-electron-microscopes-368293
<p>ɬ has mandated Construction Bralteck to carry out Project 21-081 Strathcona Anatomy and Dentistry – CFI Ortega, which involves the fit-up of rooms B/31, B/32B, B/27, and B/2F within the Facility for Electron Microscopy Research (FEMR), to accommodate two new microscopes.</p>Fri, 10 Oct 2025 19:47:00 +0000anthony.minicozzi@mcgill.ca1826 at /facilitiesConstruction Starts: McIntyre Medical Building – Renovation of the 6th floor
/facilities/channels/news/construction-starts-mcintyre-medical-building-renovation-6th-floor-369908
<p>ɬ has mandated Les Constructions Serbec Inc. to carry out<strong> Project 25-001</strong>, which involves the renovation of the 6th floor of the McIntyre Building as part of the Medicine cohort increase initiative. This work will reconfigure the existing floor to accommodate seven new hybrid classrooms dedicated to Clinical Skills Training, integrating in-person instruction with educational technology.</p>Wed, 17 Dec 2025 16:22:58 +0000anthony.minicozzi@mcgill.ca1837 at /facilitiesConstruction starts: Neuro Montreal – 9.4T MRI installation
/facilities/channels/news/construction-starts-neuro-montreal-94t-mri-installation-368108
<p>ɬ has mandated SDI Canada to carry out Project 21-094, which involves the installation of a new 9.4T MRI in the Webster Pavilion of the Montreal Neurological Institute.</p>
<p>The project will renovate and transform laboratory spaces WB306 and its adjacent rooms WB305 and WB307 to house the new MRI. A new HVAC system will also be installed on the Webster roof to provide cooling, heating, and humidification. Once complete, the facility will expand ɬ’s research capacity in neuroscience and imaging.</p>Wed, 01 Oct 2025 15:19:08 +0000anthony.minicozzi@mcgill.ca1823 at /facilitiesConstruction starts: 680 Sherbrooke – Upgrades to parking access and EV infrastructure
/facilities/channels/news/construction-starts-680-sherbrooke-upgrades-parking-access-and-ev-infrastructure-368903
<p>ɬ has mandated St-Denis Thompson to carry out <strong>Project 18-013</strong>, which involves the renovation of the parking island and surrounding area at 680 Sherbrooke West. This work will include the installation of new parking access and exit equipment, as well as the introduction of four electric vehicle (EV) chargers, which will bring EV charging infrastructure to this garage for the first time.</p>Thu, 13 Nov 2025 19:08:47 +0000anthony.minicozzi@mcgill.ca1831 at /facilitiesConstruction starts: McConnell Engineering Building – CFI IF 2023 Liboiron laboratory upgrades
/facilities/channels/news/construction-starts-mcconnell-engineering-building-cfi-if-2023-liboiron-laboratory-upgrades-370066
<p>ɬ has mandated Entreprises NR Brosseau Inc. to carry out <strong>Project 21-078</strong>, which involves upgrades within the McConnell Engineering Building as part of the CFI IF 2023 – Liboiron initiative. The project focuses on the installation of new specialized research equipment in two existing dry laboratories: Room MC010 and Room 816.</p>Mon, 05 Jan 2026 16:34:45 +0000anthony.minicozzi@mcgill.ca1838 at /facilitiesConstruction Start: SIM Centre – Medicine Cohort increase
/facilities/channels/news/construction-start-sim-centre-medicine-cohort-increase-366158
<p>Please be advised that ɬ has mandated CORENOV CONSTRUCTEURS INC.<b> </b>under the supervision of <b>RE</b><b>D</b><b>BOURNE </b>to carry out the following project: <b>24-040 SIM Center – Medicine Cohort increase.</b></p>
<p><b>Description:</b> The project includes creation of a satellite facility in leased space, transformation of existing space, and the use of technology for multi-space connectivity.</p>
<p><b>Construction start date: </b>August 4th, 2025</p>
<p><b>Planned construction end date: </b>End of December 2025</p>Tue, 29 Jul 2025 17:07:28 +0000anthony.minicozzi@mcgill.ca1820 at /facilitiesConstruction Start: Rutherford Physics - Renovation of Room 419
/facilities/channels/news/construction-start-rutherford-physics-renovation-room-419-366154
<p>Please be advised that ɬ has mandated CORENOV CONSTRUCTEURS INC.<b> </b>to carry out the following project: <b>21-053 Rutherford Physics - CFI IF 2023 Childress, Renovation of Room 419</b></p>
<p><b>Description:</b> Room 419 is already an existing research laboratory. It has two smaller rooms inside of it but the walls will be demolished to create one large room. The room will be updated to meet the ɬ Design Standards for a research laboratory and it will be reconfigured to meet laser lab requirements as well.</p>Tue, 29 Jul 2025 14:17:44 +0000anthony.minicozzi@mcgill.ca1818 at /facilitiesConstruction Starts: Trottier Space Institute Extension
/facilities/channels/news/construction-starts-trottier-space-institute-extension-366142
<p>Please be advised that ɬ has mandated general contractor SUTERA INC. to carry out the following project: <b>20-069 Trottier Space Institute extension.</b></p>Mon, 28 Jul 2025 19:11:21 +0000roberta.grimmtrotta@mcgill.ca1816 at /facilitiesConstruction Starts: CFI IF Tufenkji – Macdonald Stewart (Macdonald Campus)
/facilities/channels/news/construction-starts-cfi-if-tufenkji-macdonald-stewart-macdonald-campus-365572
<p>Please be advised that ɬ has mandated Corenov Construction to carry out the following project: <b>21-089 – CFI IF Tufenkji – Macdonald Stewart </b>(Macdonald Campus).</p>
<p><b>Description: </b>Partial renovation of laboratory MS3-025.</p>
<p><b>Construction start date: </b>June 9th, 2025</p>
<p><b>Planned construction end date: </b>July, 2025</p>
<p><b>Work schedule: </b>Monday to Friday, 6 a.m. to 3 p.m.</p>Mon, 02 Jun 2025 14:59:49 +0000roberta.grimmtrotta@mcgill.ca1814 at /facilitiesConstruction Starts: Lyman Duff - CFI Ernst
/facilities/channels/news/construction-starts-lyman-duff-cfi-ernst-365532
<p>Please be advised that ɬ has mandated Concept P.V.R. to carry out the following project: <b>21-028 - Lyman Duff - CFI Ernst</b></p>
<p><b>Description: </b>Renovation of existing laboratories on the 6th and 7th floors to support Dr. Ernst’s research and CFI equipment.</p>
<p><b>Construction start date: </b>June 5th 2025</p>
<p><b>Planned construction end date: </b>June 30th 2026<b> </b></p>
<p><b>Work schedule: </b>Monday to Friday, 7am to 9pm. Works outside of building hours will be coordinated in advance<b>. </b></p>Tue, 27 May 2025 19:44:46 +0000roberta.grimmtrotta@mcgill.ca1812 at /facilitiesConstruction Starts: Wong - CFI JELF Oct 2022, Huberman – Lab 5270
/facilities/channels/news/construction-starts-wong-cfi-jelf-oct-2022-huberman-lab-5270-365531
<p><i>Please be advised that ɬ has mandated CORENOV Contractors to carry out the work associated with the project hereafter: </i><strong><i>22-013 Wong - CFI JELF Oct 2022, Huberman - Lab 5270</i></strong></p>
<p><b>Description: </b><i>To construct a laser enclosure in Laboratory 5270 and integrate its services with the building’s existing infrastructure. </i></p>
<p><b>Construction start date: </b><i>May 14, 2025 </i></p>
<p><b>Planned construction end date: </b><i>July 04, 2025 </i></p>
<p><b>Work schedule: </b><i>Monday to Friday, 7 a.m. to 3 p.m. </i></p>Tue, 27 May 2025 19:34:43 +0000roberta.grimmtrotta@mcgill.ca1810 at /facilitiesConstruction Starts: New Residence Hall - Emergency Facade Work and Facade Renovation
/facilities/channels/news/construction-starts-new-residence-hall-emergency-facade-work-and-facade-renovation-365192
<p>Please be advised that ɬ has mandated St-Denis Thompson Inc to carry out the following project: <b>18-103 New Residence Hall - Restoration of Facades – PHASE 2</b></p>
<p><b>Description: </b>Complete replacement of block facing on building facades and repair of concrete surfaces.</p>
<p><b>Construction start date: </b>May 5, 2025</p>
<p><b>Planned construction end date: </b>End of 2026</p>
<p><b>Work schedule: </b></p>Tue, 29 Apr 2025 14:51:09 +0000roberta.grimmtrotta@mcgill.ca1807 at /facilitiesConstruction Starts: Duff, CFI IF 2023, Siegel
/facilities/channels/news/construction-starts-duff-cfi-if-2023-siegel-365119
<p>Please be advised that ɬ has mandated CORENOV CONSTRUCTEURS to carry out the following project: <b>23-027 Duff, CFI IF 2023, Siegel</b></p>
<p><b>Description: </b><i>Renovation of lab 615 including replacement of ceiling tiles, repairs to floors/walls, installation of new lab bench and sink</i></p>
<p><b>Construction start date: </b>April 28, 2025</p>
<p><b>Planned construction end date: </b>End of May 2025</p>
<p><b>Work schedule: </b><i>Monday to Friday, 7 a.m. to 3 p.m.</i></p>Thu, 24 Apr 2025 15:10:32 +0000roberta.grimmtrotta@mcgill.ca1805 at /facilitiesSpring shoulder season
/facilities/channels/news/spring-shoulder-season-364737
<p>We are entering the “spring shoulder season” from early April to May, the time of the year where we switch from heating our buildings to cooling them. During this transition, your workspace or study space may become warm when the outdoor temperature rises or feel cool if temperatures drop in the coming weeks. We also want to inform all building directors that this preparation prioritizes preventative maintenance activities related to upcoming shoulder season, therefore it may lead to longer completion timelines for some of the work you request.</p>
<p><b>Inquiries</b></p>Fri, 04 Apr 2025 15:41:43 +0000roberta.grimmtrotta@mcgill.ca1803 at /facilitiesConstruction (Re)Starts: Reconstruction of Upper Main Road - Downtown Campus
/facilities/channels/news/construction-restarts-reconstruction-upper-main-road-downtown-campus-364637
<p>Please be advised that, following a winter break, construction work will resume with<strong> </strong>Ceveco Inc. to carry out the following project: <b>19-016 Reconstruction of Upper Main Road, Downtown Campus.</b></p>
<p><b>Description: </b>Reconstruction of the Upper Main Road, from the Y intersection to the McCall MacBain Arts Building, including underground work.</p>
<p><b>Construction restart date: </b>March<b> </b>31, 2025</p>
<p><b>Planned construction end date: </b>November 2025</p>
<p><b>Work schedule: </b>Monday to Friday, 6 a.m. to 7 p.m. / Saturday, 6 a.m. to 7 p.m.</p>Mon, 31 Mar 2025 20:27:13 +0000roberta.grimmtrotta@mcgill.ca1797 at /facilities